pouring the roof and raising the floor

beach wall necessary to stop erosion again

tree house floor, way up in the trees!

support beam for the cantilevered roof that will have a u-shaped cut-out for the bbq

beach wall, filling in with 'pata pata' shells, then a light concrete slurry, the covered with thick nice sand!

sideways pic of tree house floor from another vantage point
the last beam formed up

restaurant skeleton


forming the roof edges. shells will hide the concrete edge and a second row of shells will hold back the soil. plants will drape and hide the shells... keeping it organic!

first half of roof! notice scalloped edges for drainage...

second half of roof getting formed up. two open arches over the booths.

supporting the form. will be pouring thick concrete with lots of rebar and wire. this is gonna be a strong arched roof!

view from the beach

an open center channel in the roof will be covered with glass that will have a stained-glass effect, casting colours across the floor and letting in the sunlight!

moving from concrete feet to concrete boots!

pouring the roof!

all poured!

finished the first side and removed the forms

removing the forms from the roof on the beach side

Saturday, May 19, 2012

beam # 4!

putting up the form for the 4th beam!

4 beams!
taking shape...

beach close to 10m undermined by cyclone and high tides, have resorted to building a retaining wall,
and will back-fill with sand...


Sunday, May 6, 2012

booths and beams...

booths formed up
forming up the first arched beam

booths and removing form

finished the first beam!






Tuesday, May 1, 2012

beam forms up



Adding the support beams...


Arched support beams....

Arched into the ground on the hill side...


finished floor pour & retaining wall

Added the back retaining wall, behind the booths. Will be topped with a rough-cut cedar ledge.

Pouring the last step...




Tuesday, April 17, 2012

poured the floor!

yesterday we finished pouring the 2nd booth floor and put in the table legs. the tables will both lower to seat level, creating a large cushioned lounge in each booth.

today we poured the main section of the restaurant floor! we were happy to have some extra help to day and had a crew of 6 along with ben.

myself, I was on drinking water duty and was particularly taken with ben's concrete feet...






Friday, April 13, 2012

keep on pourin'...

we've been busy pouring concrete floors the last few days!
we now have two steps by the bbq, the floor for the northern seating area, the center walkway between the kitchen and the main restaurant floor, and the storage/reception bay between the booths and the kitchen.
we hopefully will pour the floor for the booths later today and then next week we'll finish the main restaurant floor slabs.
a very dramatic difference to the eye this week after taking such a long break to work on boats!